DESIGN AND PROJECT ENGINEERING



                         Consultancy service for design and development of high concentration slurry
                                                   disposal (HCSD) system.
               Sasan  Power  Ltd.,  Sasan,  Singrauli,  MP  under  Reliance   disposal sites. Our department carried out all the required
               Power offered a consultancy project to IMMT to carry out   experiments and computations on the coal ash samples
               the Rheology of their coal ash slurry samples and provide   provided by the client to determine the pressure drop for
               Basic  Design  Engineering  for  their  High  Concentration   the proposed layout, considering elevation head, start-up
               Slurry Disposal (HCSD) system. As per the proposed layout   pressure and pipeline losses. Finally, a recommendation
               shared by the client, a total of 20 km of 400 NB cast basalt   on  the  number  of  pumps  required  along  the  line  and
               lined pipeline has to be laid from the power plant area   the  optimum  distance  between  them,  along  with  other
               to the mines gate  and a total of 10.5 km  of the same   important parameters for satisfactory performance of the
               diameter pipeline has to be laid from mines gate to the two   system has been provided to the client.





















                Particle  size  distribution  of  representative  ESP  fly  ash   Variation of pH with mixing time for ESP mixed fly ash
                    samples prepared from 1st to 7th fields’ fly ash  slurry samples in distilled water medium (pH=6.3) at
                                                                         wt. concentrations of 70% and 75%




















                        Rheogram of mixed ESP fly ash slurry,     Time taken for re-suspension of mixed ESP ash slurry,
                                 Cw = 70% - 78%                                     seconds

                  Rheological investigation of Ash dyke fly ash samples for pipe line transportation at BALCO,
                                                Korba, and Chhattisgarh state.

               BALCO, Thermal Power Plant, Korba, Chhattisgarh under   with  rheological  properties,  material  density,  maximum
               Vedanta  Alumina  Ltd.,  offered  a  consultancy  project   static  settled  concentration,  stabilized  pH,  mixing  time
               to  carry  out  a  rheological  investigation  of  their  fly  ash   and energy required for re-suspension and pressure drop
               and  bottom  ash  samples  for  both  1200  MW  and  540   for different pipe sizes and solids throughput were also
               MW  power  plants.  Under  this  project,  the  rheological   studied for the coal ash samples supplied by the client.
               properties were studied for coal ash slurries at different   Based on the studies carried out, basic design engineering
               solids  concentrations,  for  both  best  coal  (with  lower   of an HCSD system and recommendations for its seamless
               ash  percentage)  and  worst  coal  (one  with  higher  ash   operation were provided to the client.
               percentage), as per the requirements of the client. Along